Computer technology
What Europe's new data centre rating means for companies renting servers
Companies that rent servers in Europe have rarely had a fair way to compare the buildings their machines sit in. An IT manager who sends a supplier questionnaire about certifications and renewable energy often gets back a link to the provider's own web page, written in that provider's terms.
A delegated regulation adopted by the European Commission on 21 September 2026 is meant to change that. It sets up an EU-wide rating for data centres, and operators will have to hand the resulting grade to anyone who asks for it.
A label for the building, from August 2027
The rating is the second step of a scheme built under the recast Energy Efficiency Directive. The first step, the 2024 reporting regulation, already requires operators of data centres with at least 500 kW of installed IT power demand to send energy and water figures to a European database every year by 15 May.
The new act turns those reports into a label. The database will generate one for each reporting site by 15 August 2027. Each label is valid for a year and is published in every official EU language.
The timing reflects rising electricity demand. EU data centres used around 68 TWh in 2024, and the Commission's announcement cites a projection of 114 TWh by 2030, more than 3% of EU demand.
The European Parliament and the Council have two months to object to the act, a period that can be extended by two more. They can reject it, but they cannot rewrite it. Until that period ends and the text is published in the Official Journal, the rating is not in force. It takes effect 20 days after publication, and no label exists yet.
Two letters and a climate figure
The first grade on the label covers power usage effectiveness (PUE), the ratio of the total energy a facility consumes to the energy used by its IT equipment. A PUE of 1.15 or less earns class A, and anything above 1.9 falls into class G. The IT side of the ratio is measured at the equipment input where possible, category 3 in the EN 50600-4-2 standard, or otherwise at the power distribution units, category 2.
The second covers water usage effectiveness (WUE), counted in litres per kilowatt-hour of IT energy. The scale runs from A at 0.1 or less to G above 1.0.
Take a server assumed, for illustration, to draw 250 W on average. It uses about 2,190 kWh a year. At a PUE of 1.15, the facility draws roughly 2,520 kWh to run it. At 1.9, the last value before class G, it draws about 4,160 kWh. That is about 65% more energy for the same machine, around 1,640 kWh a year, all of it consumed by cooling, power conversion and other building loads.
Beside the two letters, the label prints the cooling degree days of the location, a measure of how warm its climate runs. It also shows how the site's electricity was sourced. Renewable and nuclear energy are each split between on-site generation, power purchase agreements and guarantees of origin, and any energy of unidentified origin is listed separately.
A further figure gives the share of those agreements and certificates tied to new generating capacity. The label also states whether the site offers flexibility services to the grid and whether it is ready to supply waste heat to an outside user.
What the letter does not show
Climate accounts for part of a data centre's PUE rating. A site in a cool region can cool its halls with outside air for much of the year and reach a low ratio with little engineering, which is why cooling degree days sit beside the letter.
The Commission will attach a common note to every label explaining how PUE relates to climate, size, age and occupancy. A newly opened hall running at half capacity spreads its fixed cooling and power losses across a small IT load, so its PUE appears worse than it will once the racks are filled.
The same note will cover the trade-off between the two grades. Evaporative cooling reduces electricity use but increases water consumption, so a site can move into a better PUE class and see its WUE deteriorate in the same year.
A site can report its consumption as fully renewable over a year by buying guarantees of origin, certificates that are not matched to consumption hour by hour, a gap critics call a loophole. Because the label shows certificates apart from power purchase agreements and on-site generation, buyers can see which kind of renewable claim they are reading.
PUE also captures only the energy overhead around the IT equipment. An idle server in a class A hall still draws power, and the rating is silent on utilisation, on sites outside the EU and on rooms under 500 kW that stay out of the scheme.
For tenants, the choice comes down to the building
The label is most useful when a workload can be pinned to one building. A dedicated server is one physical machine in one facility, and the location is usually stated when the order is placed.
An OVHcloud dedicated server, for instance, sits in a named data centre, so that site's label covers the whole machine. The provider's own figures for its 2025 financial year show why the site matters, with a PUE of 1.19 at Strasbourg and Limburg against 1.30 at Roubaix.
Services spread across several sites are harder to read. When a workload moves between buildings, no single label describes it, and the buyer has to ask which sites carry the load and in what proportion.
Article 4 of the new act will require operators to provide the label in electronic form to any person who requests it, on their own website or through the European database. Customers renting a server have no reporting duty of their own; the obligations sit with the operator.
Colocation customers are in a different position, as they install and operate their own equipment. A colocation operator that cannot measure the whole computer room will have to state what share of the floor area its figures cover, and may collect figures from its customers anonymously.
Questions for the next contract renewal
Procurement teams can use the grade well before any binding standard exists. Legal advisers to operators expect weak grades could surface in procurement and financing talks. A company reviewing a bare metal dedicated server contract before the first labels appear can put five questions to its provider:
- Which building, in which country, hosts the machine?
- Is that site at or above 500 kW, and does it report to the European database?
- What are its PUE and WUE classes, and its cooling degree days?
- What share of its electricity is covered by guarantees of origin, and what share by power purchase agreements or on-site generation?
- Is the site ready to supply waste heat, and does it offer flexibility to the grid?
A minimum standard may follow. The Commission is consulting on minimum performance standards for new or retrofitted data centres until 14 December 2026, with a proposal planned for the second quarter of 2027.
Photo: İsmail Enes Ayhan / Unsplash
Share this article:
EU Reporter publishes articles from a variety of outside sources which express a wide range of viewpoints. The positions taken in these articles are not necessarily those of EU Reporter. Please see EU Reporter’s full Terms and Conditions of publication for more information EU Reporter embraces artificial intelligence as a tool to enhance journalistic quality, efficiency, and accessibility, while maintaining strict human editorial oversight, ethical standards, and transparency in all AI-assisted content. Please see EU Reporter’s full A.I. Policy for more information.
-
Albania4 days agoAlbania could conclude EU accession talks by 2027, but must reverse reform slowdown
-
China-EU5 days agoEurope and China can build a fairer trading relationship through cooperation
-
Health4 days agoMore than 200 businesses urge von der Leyen to rethink EU tobacco rules
-
European Commission4 days agoCommission defends targeted 2027 work programme as focus shifts to delivery