Commission should apply lessons learned from its development of Schengen Info System to avoid similar delays and overspending on future IT projects, say EU Auditors
European Court of Auditors (ECA) special reports are published throughout the year, presenting the results of selected audits of specific EU budgetary areas or management topics.
This special report (No 3/2014) entitled Lessons from the European Commission’s development of the second generation Schengen Information System (SIS II), examined why the Commission delivered SIS II over six years later than planned and at a cost far exceeding the initial estimates. It also examined whether there was a robust business case for SIS II throughout the project, which took into account major changes to the costs and expected benefits. In addition, the EU auditors assessed whether the Commission had learnt and applied lessons from its management of the project.
The EU auditors found that the delay and overspend resulted from deficiencies in the Commission’s management in a challenging governance context, particularly during the first part of the project up until 2009. Despite major changes to the costs and expected benefits during the project, the Commission did not reassess the business case in order to demonstrate that SIS II remained an organisational priority which provided a higher return on investment than other opportunities. There was no decision, based on a reassessment of costs and benefits, on whether to continue with, or stop, the project. The Commission learnt lessons from its experience during the first part of the project in order to change its approach during the final project phase from 2010 and to deliver SIS II in April 2013.
Based on its findings, the ECA recommended that, when managing the development of large-scale IT systems, the Commission should:
- Base the timetable on a technical analysis of the tasks to be performed;
- ensure that all projects are integrated into corporate IT governance arrangements and make full use of in-house expertise to manage the work of contractors effectively;
- ensure that business needs and the views of end users are sufficiently taken into account in decision-making;
- ensure the approval of the business case before progressing from project initiation to project planning and its reapproval in the event of major changes to project costs, expected benefits, risks or alternatives;
- ensure that key project decisions are documented in a decision log so that they are easily traceable;
- ensure that there is effective global co-ordination when a project requires the development of different but dependent systems by different stakeholders;
- develop large-scale IT systems using interoperable building blocks which can easily be re-used to prevent being locked-in to a single contractor, and;
- pass on the lessons learnt from the Court’s audit to DGs and EU institutions, agencies and other bodies. The Commission should evaluate whether the expected benefits of SIS II were achieved.
A short video interview with the ECA Member responsible for the report is available here.
Share this article:
EU Reporter publishes articles from a variety of outside sources which express a wide range of viewpoints. The positions taken in these articles are not necessarily those of EU Reporter. Please see EU Reporter’s full Terms and Conditions of publication for more information EU Reporter embraces artificial intelligence as a tool to enhance journalistic quality, efficiency, and accessibility, while maintaining strict human editorial oversight, ethical standards, and transparency in all AI-assisted content. Please see EU Reporter’s full A.I. Policy for more information.